Since construction began in late May, we’ve built more than 50 miles of fiber and installed three of nine fiber huts. Fiber huts will house all electronics used to provide fiber internet to customers on the substation.
We now have over 3,000 pre-registrations. Service is on schedule to go live for Zone 1 in August, followed by Zone 2 in September. Projected Service Schedule: Tri-Co Go